The cost estimate for construction of a 0.5 ha ETS is shown in Table-6.
|
Sl.
|
Particulars
|
Quantity
|
Unit rate (Rs)
|
Amount (Rs)
|
|
1
|
Earth work excavation and laying in embankments for dykes and baffle walls as per design, with compaction, dressing, etc.
|
4700 cu.m
|
60/-
|
228 200/-
|
|
2
|
Sluice gate - Main - Secondary
|
1 No. 3 Nos.
|
30 000/- 15 000/-
|
30 000/- 45 000/-
|
|
3
|
Sump Pit
|
L.S.
|
|
35 000/-
|
|
4
|
Supplying and installing M.F. pump- 10 HP with accessories complete
|
1 No.
|
60 000/-
|
60 000/-
|
|
5
|
Supplying and installing paddle wheel aerators including cables, etc
|
2 Nos.
|
30 000/-
|
60 000/-
|
|
6
|
Pumps shed and electrical works
|
L.S.
|
-
|
50 000/-
|
|
7
|
Miscellaneous
|
L.S.
|
-
|
40 000/-
|
| |
Total
|
|
|
548 200/- or say 550 000/-
|
Land and operational costs are not included. The costs are indicative and may vary from location to location.
|
|
|
|
| |
|